EPC Projects

Dredging work in front of berth No.27

Client
ICTSI/ BGT
Start Date
11/05/2017
Contract
Unit price
Duration
6 Months

A total of 800,000 cubic meters of materials were dredged in front of berth 27 to reach to navigational depths in accordance with requirement of Umm Qasr port navigational depths. IHC suction cutter dredgers were used with a maximum dredging depth of 16 meters and in/out suction pipe of 600mm